Factory renovation

Kocaeli · Year: 2025 · In progress

Year

2025

City

Kocaeli

Duration

Phased, 9 months total

Area (GFA)

~6,200 m²

Factory renovation

Summary

Strengthening and new façade cladding while keeping production lines running.

A phased plan minimized operational downtime. Steel strengthening and new sandwich-panel façade improved energy efficiency.

Production bays were brought online sequentially with dust and noise controls on night shifts; machine footings and vibration checks were monitored throughout.